Roadmap

2023
June

System architecture fully defined

All key elements of the system architecture and key interfaces are defined, system level requirements are fixed and aligned with project ambition and Aircraft requirements and sufficient to start decompostion to system component level and development of subsystems.

2024
December

All components ready for subsystem integration

All components are designed, developed and ready for integration into the subsystems to enable functional validation on subsystem level. Testing infrastructure in place to validate individual subsystems.

2025
November

Subsystems integrated into the demonstrator

Subsystem validation finished and integrated into the complete propulsion system demonstrator. Ready for system level integration testing to validate overall system functionality and performance.

2026
February

Ground demonstrator fully operational

All the subsystems integrated into the final demonstrator and the final system is ready for safe operation and final validation.

2026
May

Demonstration testing finished

The overall integrated system demonstrator functional testing complete. Performance characterization testing complete.